Vegetation management on a transmission system is never truly finished. Every single structure cycles through inspection, treatment, and follow-up. Every step depends entirely on what the previous step uncovered in the field.
When those field decisions live buried inside individual reports, program managers lose visibility fast. You cannot see what each structure needs next, you cannot verify if the planned work matches what crews actually completed in the field, and you completely lose track of where each structure stands in its long-term inspection cycle.
At LS Power, every transmission structure acts as a living asset in KYRO AI, and that central asset record drives all the work. The result is 2,151 structures seamlessly carried through a manager-directed cycle of inspection, treatment, and maintenance, ensuring no structure is ever scheduled twice.
LS Power is a transmission owner currently running three major field programs in KYRO AI: vegetation management and structure upkeep on standing lines, new transmission line construction, and substation inspections. Crucially, all three programs share one unified asset inventory.
The vegetation program carries 2,151 structures through a continuous cycle of annual inspections, ground inspections, treatments, and post-treatments. LS Power needed its managers to see exactly what activity each structure required next without forcing them to open dozens of individual reports. They also needed daily treatment plans to match reality, and inspection cycles that did not rely on someone updating a spreadsheet by hand.
Crews submit their field findings directly into KYRO AI. The platform then writes those results straight back to each structure's permanent record. This allows managers to dictate the next activity for every structure from one simple, consolidated table.

A transmission owner maintains vegetation along its lines year after year. Without a central asset record driving that workflow, managers end up scheduling work based on scattered reports. Daily plans drift away from what crews accomplish in the field, and multi-year inspection cycles depend entirely on human memory.
KYRO AI put the structure's own digital record right at the center of LS Power's vegetation program. Findings flow in from the field, results write back automatically, and every structure's next activity gets scheduled from one clear table.
That is exactly why KYRO AI exists.
How does KYRO AI set a structure's next vegetation activity? When a crew submits a form, KYRO AI copies the key findings into task fields for the manager to review. The manager picks a next step and completes the task. KYRO AI then writes the results back to the structure's asset record and automatically sets its next scheduled vegetation activity.
What happens when a treatment crew treats more or fewer structures than planned? KYRO AI reads which structures were actually treated directly from the field submission. Extra structures are moved onto that day's task from any other future task they were planned under. Untreated structures seamlessly move to the crew member's next task by due date, or to a brand new task if none exist.
How does KYRO AI stop a structure from being scheduled twice? When a manager creates a project for a structure's next activity, KYRO AI resets that structure's "Next Vegetation Activity" status to none. A structure that is already scheduled simply no longer shows up as waiting for work.